Correct Answer
verified
Multiple Choice
A) If the WACC is 6%, Project S will have the higher NPV.
B) If the WACC is 13%, Project S will have the lower NPV.
C) If the WACC is 10%, both projects will have a negative NPV.
D) Project S's NPV is more sensitive to changes in WACC than Project L's.
E) If the WACC is 10%, both projects will have positive NPVs.
Correct Answer
verified
Multiple Choice
A) 14.08%
B) 15.65%
C) 17.21%
D) 18.94%
E) 20.83%
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method versus the NPV is that the IRR does not take account of the time value of money.
B) One defect of the IRR method versus the NPV is that the IRR does not take account of the cost of capital.
C) One defect of the IRR method versus the NPV is that the IRR values a dollar received today the same as a dollar that will not be received until sometime in the future.
D) One defect of the IRR method versus the NPV is that the IRR does not take proper account of differences in the sizes of projects.
E) One defect of the IRR method versus the NPV is that the IRR does not take account of cash flows over a project's full life.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) If a project has "normal" cash flows, then its MIRR must be positive.
B) If a project has "normal" cash flows, then it will have exactly two real IRRs.
C) The definition of "normal" cash flows is that the cash flow stream has one or more negative cash flows followed by a stream of positive cash flows and then one negative cash flow at the end of the project's life.
D) If a project has "normal" cash flows, then it can have only one real IRR, whereas a project with "nonnormal" cash flows might have more than one real IRR.
E) If a project has "normal" cash flows, then its IRR must be positive.
Correct Answer
verified
Multiple Choice
A) 1.91 years
B) 2.12 years
C) 2.36 years
D) 2.59 years
E) 2.85 years
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $185.90
B) $197.01
C) $208.11
D) $219.22
E) $230.32
Correct Answer
verified
Multiple Choice
A) Ignores cash flows beyond the payback period.
B) Does not directly account for the time value of money.
C) Does not provide any indication regarding a project's liquidity or risk.
D) Does not take account of differences in size among projects.
E) Lacks an objective, market-determined benchmark for making decisions.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.86 years
B) 2.07 years
C) 2.30 years
D) 2.53 years
E) 2.78 years
Correct Answer
verified
Multiple Choice
A) You should recommend that the project be rejected because, although its NPV is positive, it has an IRR that is less than the WACC.
B) You should recommend that the project be accepted because (1) its NPV is positive and (2) although it has two IRRs, in this case it would be better to focus on the MIRR, which exceeds the WACC.You should explain this to the president and tell him that the firm's value will increase if the project is accepted.
C) You should recommend that the project be rejected.Although its NPV is positive it has two IRRs, one of which is less than the WACC, which indicates that the firm's value will decline if the project is accepted.
D) You should recommend that the project be rejected because, although its NPV is positive, its MIRR is less than the WACC, and that indicates that the firm's value will decline if it is accepted.
E) You should recommend that the project be rejected because its NPV is negative and its IRR is less than the WACC.
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always less than its regular IRR.
B) If a project's IRR is greater than its WACC, then the MIRR will be less than the IRR.
C) If a project's IRR is greater than its WACC, then the MIRR will be greater than the IRR.
D) To find a project's MIRR, we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the WACC.
E) A project's MIRR is always greater than its regular IRR.
Correct Answer
verified
Multiple Choice
A) $188.68
B) $198.61
C) $209.07
D) $219.52
E) $230.49
Correct Answer
verified
Multiple Choice
A) Project D is probably larger in scale than Project C.
B) Project C probably has a faster payback.
C) Project C probably has a higher IRR.
D) The crossover rate between the two projects is below 12%.
E) Project D probably has a higher IRR.
Correct Answer
verified
Multiple Choice
A) If the cost of capital is greater than the crossover rate, then the IRR and the NPV criteria will not result in a conflict between the projects.The same project will rank higher by both criteria.
B) If the cost of capital is less than the crossover rate, then the IRR and the NPV criteria will not result in a conflict between the projects.The same project will rank higher by both criteria.
C) For a conflict to exist between NPV and IRR, the initial investment cost of one project must exceed the cost of the other.
D) For a conflict to exist between NPV and IRR, one project must have an increasing stream of cash flows over time while the other has a decreasing stream.If both sets of cash flows are increasing or decreasing, then it would be impossible for a conflict to exist, even if one project is larger than the other.
E) If the two projects' NPV profiles do not cross, then there will be a sharp conflict as to which one should be selected.
Correct Answer
verified
Multiple Choice
A) $41.25
B) $45.84
C) $50.93
D) $56.59
E) $62.88
Correct Answer
verified
Showing 81 - 100 of 108
Related Exams