A) 36%
B) 32%
C) 28%
D) 24%
E) 20%
Correct Answer
verified
Multiple Choice
A) Is useless as a risk indicator.
B) Ignores cash flows beyond the payback period.
C) Does not directly account for the time value of money.
D) All of the above are correct.
E) Only answers b and c are correct.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $10,000
B) $12,000
C) $15,680
D) $16,000
E) $18,000
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) −$8,980
B) −$6,460
C) −$5,200
D) −$6,840
E) −$12,020
Correct Answer
verified
Multiple Choice
A) 12.00%
B) 15.53%
C) 18.62%
D) 19.08%
E) 20.46%
Correct Answer
verified
Multiple Choice
A) −$22,180
B) −$30,000
C) −$33,600
D) −$36,000
E) −$40,000
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The NPV will be positive if the IRR is less than the required rate of return.
B) If the multiple IRR problem does not exist, any independent project acceptable by the NPV method will also be acceptable by the IRR method.
C) When IRR = r (the required rate of return) , NPV = 0.
D) The IRR can be positive even if the NPV is negative.
E) The NPV method is not affected by the multiple IRR problem.
Correct Answer
verified
Multiple Choice
A) Expected NPV = $35,000; σNPV = 17,500; CVNPV = 2.0.
B) Expected NPV = $35,000; σNPV = 11,667; CVNPV = 0.33.
C) Expected NPV = $10,300; σNPV = 12,083; CVNPV = 1.17.
D) Expected NPV = $13,900; σNPV = 8,476; CVNPV = 0.61.
E) Expected NPV = $10,300; σNPV = 13,900; CVNPV = 1.35.
Correct Answer
verified
Multiple Choice
A) $6.24
B) $7.89
C) $8.87
D) $9.15
E) $10.41
Correct Answer
verified
Multiple Choice
A) Equal to the internal rate of return.
B) Too high.
C) Greater than the internal rate of return.
D) Too low.
E) Less than the internal rate of return.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) B with a NPV of $10,001.
B) Both A and B because both have NPVs greater than zero.
C) B with a NPV of $8,042.
D) A with a NPV of $7,177.
E) A with a NPV of $15,968.
Correct Answer
verified
Multiple Choice
A) $2,622
B) $2,803
C) $2,917
D) $5,712
E) $6,438
Correct Answer
verified
Multiple Choice
A) Changes in working capital attributable to the project.
B) Previous expenditures associated with a market test to determine the feasibility of the project, if the expenditures have been expensed for tax purposes.
C) The current market value of any equipment to be replaced.
D) The resulting difference in depreciation expense if the project involves replacement.
E) All of the above should be considered.
Correct Answer
verified
Multiple Choice
A) In a capital budgeting analysis where part of the funds used to finance the project are raised as debt, failure to include interest expense as a cost when determining the project's supplemental operating cash flows will lead to an upward bias in the NPV.
B) The preceding statement would be true if "upward" were replaced with "downward."
C) The existence of "externalities" reduces the NPV to a level below the value that would exist in the absence of externalities.
D) If one of the assets that would be used by a potential project is already owned by the firm, and if that asset could be leased to another firm if the project is not undertaken, then the net rent that could be obtained should be charged as a cost (initial investment outlay) to the project under consideration.
E) The rent referred to in statement d is a sunk cost, and as such it should be ignored.
Correct Answer
verified
Showing 61 - 80 of 201
Related Exams