A) slope.
B) intercept.
C) dependent variable.
D) independent variable.
Correct Answer
verified
Essay
Correct Answer
verified
Multiple Choice
A) intercept
B) setup hours
C) number of parts
D) All of the above are significant
Correct Answer
verified
Multiple Choice
A) £19,400.
B) £20,500.
C) £19,950.
D) none of the above.
Correct Answer
verified
Multiple Choice
A) the estimated monthly total costs of the sales department.
B) the estimated monthly fixed costs of the sales department.
C) the estimated monthly variable costs per unit of the sales department.
D) the percent of variation in Y that is explained by X.
Correct Answer
verified
Multiple Choice
A) Only two observations are used to develop the cost function.
B) The high and low activity levels may not be representative.
C) The method does not detect if the cost behaviour is nonlinear.
D) The method is easy to apply.
Correct Answer
verified
Multiple Choice
A) is linear.
B) must be tested for minima and maxima.
C) is parabolic.
D) is quadratic.
Correct Answer
verified
Multiple Choice
A) slope.
B) intercept.
C) dependent variable.
D) independent variable.
Correct Answer
verified
Multiple Choice
A) 100 hours
B) 80 hours
C) 20 hours
D) 60 hours
Correct Answer
verified
Multiple Choice
A) £24,000
B) £42,000
C) £30,000
D) £12,000
Correct Answer
verified
Multiple Choice
A) £288,000
B) £296,000
C) £256,000
D) £320,000
Correct Answer
verified
Multiple Choice
A) A correlation equal to -1 means two alternatives are moving in the same direction, whereas a correlation of 0 means they are moving in opposite directions.
B) A correlation equal to -1 means two alternatives are moving in the same direction, whereas a correlation of 0 means they are unrelated.
C) A correlation equal to -1 means two alternatives are moving in opposite directions, whereas a correlation of 0 means they are moving in the same direction.
D) A correlation equal to -1 means two alternatives are moving in opposite directions, whereas a correlation of 0 means they are unrelated.
Correct Answer
verified
Essay
Correct Answer
verified
Multiple Choice
A) Overhead = 1,000 + 25(Setup hours) + 100(# of parts) .
B) Overhead = 510 + 0.305(Setup hours) + 10.527(# of parts) .
C) Overhead = 0.98 + 40.98(Setup hours) + 4.865(# of parts) .
D) Overhead = 1,000 + 25(Setup hours) .
Correct Answer
verified
Multiple Choice
A) is influenced by extreme observations.
B) requires the use of judgment.
C) uses the least-squares method.
D) is superior to other methods in its ability to distinguish between discretionary and committed fixed costs.
Correct Answer
verified
Multiple Choice
A) a statistical method is used to mathematically derive the cost function.
B) only two points are used to develop the cost function.
C) the squared differences between actual observations and the line (cost function) are minimized.
D) all the observations have an effect on the cost function.
Correct Answer
verified
Multiple Choice
A) slope.
B) intercept.
C) dependent variable.
D) independent variable.
Correct Answer
verified
Multiple Choice
A) intercept.
B) slope.
C) coefficient of determination.
D) correlation coefficient.
Correct Answer
verified
Multiple Choice
A) total variable costs.
B) total direct labour hours.
C) total factory overhead.
D) total fixed costs.
Correct Answer
verified
Multiple Choice
A) slope.
B) intercept.
C) dependent variable.
D) total variable costs.
Correct Answer
verified
Showing 41 - 60 of 63