Correct Answer
verified
Multiple Choice
A) If the WACC is 9%, Project A's NPV will be higher than Project B's.
B) If the WACC is 6%, Project B's NPV will be higher than Project A's.
C) If the WACC is greater than 14%, Project A's IRR will exceed Project B's.
D) If the WACC is 9%, Project B's NPV will be higher than Project A's.
E) If the WACC is 13%, Project A's NPV will be higher than Project B's.
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method versus the NPV is that the IRR does not take account of the time value of money.
B) One defect of the IRR method versus the NPV is that the IRR does not take account of the cost of capital.
C) One defect of the IRR method versus the NPV is that the IRR values a dollar received today the same as a dollar that will not be received until sometime in the future.
D) One defect of the IRR method versus the NPV is that the IRR does not take proper account of differences in the sizes of projects.
E) One defect of the IRR method versus the NPV is that the IRR does not take account of cash flows over a project's full life.
Correct Answer
verified
Multiple Choice
A) If a project's IRR is equal to its WACC, then under all reasonable conditions, the project's IRR must be negative.
B) If a project's IRR is equal to its WACC, then under all reasonable conditions the project's NPV must be zero.
C) There is no necessary relationship between a project's IRR, its WACC, and its NPV.
D) When evaluating mutually exclusive projects, those projects with relatively long lives will tend to have relatively high NPVs when the cost of capital is relatively high.
E) If a project's IRR is equal to its WACC, then, under all reasonable conditions, the project's NPV must be negative.
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the risk-free rate, while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the risk-free rate.
C) The NPV method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
D) The IRR method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
E) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the IRR.
Correct Answer
verified
Multiple Choice
A) If a project has "normal" cash flows, then its MIRR must be positive.
B) If a project has "normal" cash flows, then it will have exactly two real IRRs.
C) The definition of "normal" cash flows is that the cash flow stream has one or more negative cash flows followed by a stream of positive cash flows and then one negative cash flow at the end of the project's life.
D) If a project has "normal" cash flows, then it can have only one real IRR, whereas a project with "nonnormal" cash flows might have more than one real IRR.
E) If a project has "normal" cash flows, then its IRR must be positive.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The crossover rate must be greater than 10%.
B) If the WACC is 8%, Project X will have the higher NPV.
C) If the WACC is 18%, Project Y will have the higher NPV.
D) Project X is larger in the sense that it has the higher initial cost.
E) The crossover rate must be less than 10%.
Correct Answer
verified
Multiple Choice
A) Since the projects are mutually exclusive, the firm should always select Project B.
B) If the crossover rate is 8%, Project B will have the higher NPV.
C) Only one project has a positive NPV.
D) If the crossover rate is 8%, Project A will have the higher NPV.
E) Each project must have a negative NPV.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The lower the WACC used to calculate a project's NPV, the lower the calculated NPV will be.
B) If a project's NPV is less than zero, then its IRR must be less than the WACC.
C) If a project's NPV is greater than zero, then its IRR must be less than zero.
D) The NPV of a relatively low-risk project should be found using a relatively high WACC.
E) A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV) , then discounting the TV at the WACC.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The higher the WACC used to calculate the NPV, the lower the calculated NPV will be.
B) If a project's NPV is greater than zero, then its IRR must be less than the WACC.
C) If a project's NPV is greater than zero, then its IRR must be less than zero.
D) The NPVs of relatively risky projects should be found using relatively low WACCs.
E) A project's NPV is generally found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting the TV at the IRR to find its PV.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) If the cost of capital is greater than the crossover rate, then the IRR and the NPV criteria will not result in a conflict between the projects. The same project will rank higher by both criteria.
B) If the cost of capital is less than the crossover rate, then the IRR and the NPV criteria will not result in a conflict between the projects. The same project will rank higher by both criteria.
C) For a conflict to exist between NPV and IRR, the initial investment cost of one project must exceed the cost of the other.
D) For a conflict to exist between NPV and IRR, one project must have an increasing stream of cash flows over time while the other has a decreasing stream. If both sets of cash flows are increasing or decreasing, then it would be impossible for a conflict to exist, even if one project is larger than the other.
E) If the two projects' NPV profiles do not cross, then there will be a sharp conflict as to which one should be selected.
Correct Answer
verified
Multiple Choice
A) Project D is probably larger in scale than Project C.
B) Project C probably has a faster payback.
C) Project C probably has a higher IRR.
D) The crossover rate between the two projects is below 12%.
E) Project D probably has a higher IRR.
Correct Answer
verified
Multiple Choice
A) One drawback of the regular payback for evaluating projects is that this method does not properly account for the time value of money.
B) If a project's payback is positive, then the project should be rejected because it must have a negative NPV.
C) The regular payback ignores cash flows beyond the payback period, but the discounted payback method overcomes this problem.
D) If a company uses the same payback requirement to evaluate all projects, say it requires a payback of 4 years or less, then the company will tend to reject projects with relatively short lives and accept long-lived projects, and this will cause its risk to increase over time.
E) The longer a project's payback period, the more desirable the project is normally considered to be by this criterion.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 59
Related Exams